Certification | Certification Requirements | Upload Requirements | Examples |
---|
Operator.VOC.MCD - VOC - Backhoe | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Concrete Placing Boom PB | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Dogger DG | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Dozer | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Dump Truck (Articulated) | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Dump Truck (Rigid) | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Elevating Work Platform | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Excavator | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Forklift | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Front End Loader | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Grader | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Non Slewing Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Personnel Hoist HP | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Piling Rig | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Portal Boom Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Rigger | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Roller | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Scaffolder | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Scissor Lift | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
Note: 'Gennie Booms and Scissors' also acceptable wording - must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Scraper | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Skid Steer | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC - Telescopic Material Handler | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- Note: 'Telehandler' is acceptable wording
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC - Water Cart | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Bridge and Gantry Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Class ‘A’ High Pressure Water Jetting Systems | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Air | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Class 1 | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Class 2 | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Core | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Directional | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Drill Rig- Directional Drilling | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Chainsaw | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Circular Saw | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Compressed Air Tools | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Explosive Power Tools | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Jumping Jack | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Plate Compactor | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Quick Cut (Demolition Saw) | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Instrument Scabbler | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Lighting towers | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – NDD (Vac Truck) | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
|
|
Operator.VOC.MCD - VOC – Piling hammers | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Self Erecting Tower Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Slewing Mobile Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Tower Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |
Operator.VOC.MCD - VOC – Vehicle Loading Crane | - Applicants name to be displayed on the document along with qualifications
- Must show operator's qualifications
- The competency must be indicated on the Verification of Competency (VOC) as it is shown in this role title of the selected role on the data application
- must include a list of assessed activities inclusive of pre-operation, operation and shut down stages of plant usage and knowledge of safety features
- Must be signed off by the verifier of the VOC
Template provided in portal however does not have to be on this template. | - Date of assessment to be recorded as Issue date within Onsite
- 1 year expiration date form date of assessment to be calculated as expiry date and recorded within Onsite
| |