Hired Plant Inspection Report - Concrete Booms & Pumps
Correct form used - LLE902G Concrete Booms & Pumps Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Cranes incl. Crane Trucks
Correct form used - LLE902H Cranes (incl. Crane Trucks) Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Earthmoving Plant
Correct form used - LLE902I Earthmoving Plant Hired Plant Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on pages 3-4 completed, signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report - EWP
Correct form used - LLE902J EWP Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Heavy Vehicle
Correct form used - LLE902K Heavy Vehicle Hired Plant Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Paving Plant
Correct form used - LLE902M Paving Plant Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Piling and Drilling Rigs
Correct form used - LLE902N Piling & Drilling Rigs Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Rail Plant
Correct form used - LLE902R Rail Plant Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
All owner checks pages 2-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report - Light Vehicles
Correct form used - LLE906E Light Vehicle Hired Plant Inspection Report
All sections of plant details box top of page 1 complete
All minimum light vehicle requirements boxes page 1 ticked and cross ticked by LLE
All owner checks pages 1-2 ticked ok. If not comments section completed
Signature boxes on page 2 completed, signed and dated by owner and LLE
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue
Hired Plant Inspection Report – Small Plant
Correct form used - LLE902P Small Plant (Including Towable Plant) Hired Plant Inspection Report
All sections of plant details box top of page 1 complete
All mandatory requirements boxes page 1 ticked and cross ticked by LLE
All owner checks pages 1-3 ticked ok. If not comments section completed
Parts of the form that are required to be signed and dated
Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'
Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document
Issue Date = As per report Expiry Date = 5 years from date of issue