Safety Management System Sub-contractor Authority Form | - All fields to be completed
- Principal Contractor and Authorized Company Representative signatures to be present with dates
| - Dates will automatically align with SMS certification
| View file |
---|
name | MACH Energy SubContractor Authority.docx |
---|
height | 250 |
---|
|
|
Resource.Contractors.Sedgman Sub-contractor Authority Form | - All fields must be completed
- The sub-contractor company name must match the registering company in the system.
- The Authorised Company Representative from the Principal Contractor, must complete the form and sign and date
- The Authorised Company Representative from the sub-contractor company, must sign and date
| - Issue date – Date signed by principle company
- Expiry date – 2 years from issue date
| |
Resource.Contractors.Thiess Sub-contractor Authority Form | - All fields to be completed
- Thiess authorised representative must print name and sign
- Authorized Company Representative must print name and sign
The following Thiess personnel are able to approve: - Michael Redman
- Beth Viertel
- Ian Edwards
- Sherelle Hendriks
| - Dates will automatically align with SMS certification
|