titleAppointment and Nomination Forms

Anchor
whcappointmentforms
whcappointmentforms

Contractor Company Supervisor Nomination Form

This business rule was last updated by WHC on 02.04.2019

  • Details:

If you have not received a Contractor Company Supervisor Nomination Form and have WHC-FRM-Contractor Engagement form V6.0 please upload the WHC-FRM-Contractor Engagement form when requested for this document.

              Contractor company: must be displayed on form and must match registered company details in system.

P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

Aust / Australia can be accepted in any of these forms if also listed as the name in the system

Ttee (means trust) this is acceptable as long as the rest of the name matches

              Contractor company supervisor: must be listed and match Form 1 and Form 2.

  • Site/Area:  must be listed as per site required - Click HERE for a list of sites;
  • WHC Contractor Owner (class B & C): must be listed;

  • WHC Contract Coordinator(s): must be listed –  at least one contract coordinator per site, the contract owner might or might not be the same for all sites listed
  • Approval (Site or Area): must have name printed, must be signed and dated. Name must match FORM 1 - Mine Operator or Delegate(Mine Site) or Relevant Manager (Off Site): Note; Version 2 - If the contract owner has signed in place of the Mine Operator or Delegate or Relevant Manager, this can be accepted.
  • Black and white or colour copy is accepted
  • The latest version of the Contractor Company Supervisor Nomination Form is issue 3.0 – version 2 and 3 can be accepted.

    Version 2 accepted until the 30.09.2019

    CertificationCertification RequirementsUpload RequirementsExamples

    Whitehaven Coal Contractor Owner Appointment Form (WHC-FRM-Contractor Owner)

    This business rule was last updated by WHC

    01/03/2021


    • Name of Appointee: Contractor Owner as listed on WHC-FRM-Contractor Engagement
    • Name of Contracting Company: Must be listed and match company registered in onsitethe system
    • This appointment applies at the following WHC Site(s) / Department(s): Site(s) must be ticked
    • WHC Contractor Owner:must complete name, signature and date.
    • Appointed By: Sign off must be completed by a Mine Operator or Delegate (Mine Site) or Relevant Manager (Off Site) associated with the relevant site/s ticked as per the Approved Authorisers list

    The latest version of this form is issue 24.0 – version 1.0 may . The next previous version can also be accepted accepted.

    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification


    Whitehaven Coal Contractor Coordinator Appointment Form (WHC-FRM-Contractor Coordinator)

    This business rule was last updated by WHC on 01/03/2021



    • Name of Appointee:Must be a WHC employee
    • Name of Contracting Company:must be listed and match registered company in Onsitethe system
    • This appointment applies at the following WHC Site(s)/Department(s):Site(s) must be ticked
    • WHC Contract Coordinator: must complete name, signature and date.
    • Appointed By: WHC Contractor Owner must match the contracting company’s WHC-FRM-Contractor Engagement


    The latest version of this form is issue 58.0 . The next previous version may can also be accepted accepted.
    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification

    Anchor
    contractorcompanysupervisornomcontractorcompanysupervisornom
    • Issue date to be recorded as Date of document signature by contracting company
    • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 - valid for 3 years

    Pegasus staff click here for additional business rule information prior to completing file verification




    Subcontractor Details

    Whitehaven Coal Contractor Owner Appointment Form (WHC-FRM-Contractor Owner)

    This business rule was last updated by WHC

    01/03/2021

    Whitehaven Coal Contractor Coordinator Appointment Form (WHC-FRM-Contractor Coordinator)

    This business rule was last updated by WHC on 01/03/2021

    • Name of Appointee:Must be a WHC employee
    • Name of Contracting Company:must be listed and match registered company in Onsite
    • This appointment applies at the following WHC Site(s)/Department(s):Site(s) must be ticked
    • WHC Contract Coordinator: must complete name, signature and date.
    • Appointed By: WHC Contractor Owner must match the contracting company’s WHC-FRM-Contractor Engagement
    The latest version of this form is issue 5.0 – previous version may also be accepted Contractor Company Supervisor Nomination Form

    This business rule was last updated by WHC on 02.04.2019

    • Details:

    If you have not received a Contractor Company Supervisor Nomination Form and have WHC-FRM-Contractor Engagement form V6.0 please upload the WHC-FRM-Contractor Engagement form when requested for this document.

                  Contractor company: must be displayed on form and must match registered company details in system.

    P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

    Aust / Australia can be accepted in any of these forms if also listed as the name in the system

    Ttee (means trust) this is acceptable as long as the rest of the name matches

                  Contractor company supervisor: must be listed and match Form 1 and Form 2.

    • Site/Area:  must be listed as per site required - Click HERE for a list of sites;
    • WHC Contractor Owner (class B & C): must be listed;
    • WHC Contract Coordinator(s): must be listed –  at least one contract coordinator per site, the contract owner might or might not be the same for all sites listed
    • Approval (Site or Area): must have name printed, must be signed and dated. Name must match FORM 1 - Mine Operator or Delegate(Mine Site) or Relevant Manager (Off Site): Note; Version 2 - If the contract owner has signed in place of the Mine Operator or Delegate or Relevant Manager, this can be accepted.
    • Black and white or colour copy is accepted

    The latest version of the Contractor Company Supervisor Nomination Form is issue 3.0 – version 2 and 3 can be accepted.

    Version 2 accepted until the 30.09.2019

    Subcontractor Details

    Issue date to be recorded as date of document approval by WHC Contractor Owner

    Expand
    titleContractor Details
    CertificationCertification RequirementsUpload RequirementsExamples

    Head Contractor Details

    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in system

    P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

    Aust / Australia can be accepted in any of these forms if also listed as the name in the system

    Ttee (means trust) this is acceptable as long as the rest of the name matches

    • Head contractor Company details to be displayed
    • Black and white or colour copy is accepted
    • Issue date to be recorded as the date of submission
    • Expiry date to be calculated as 6 months from Issue date
    Anchor
    subcontractorformsubcontractorform
    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in system

    P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

    Aust / Australia can be accepted in any of these forms if also listed as the name in the system

    Ttee (means trust) this is acceptable as long as the rest of the name matches

    • Subcontractor Company details to be displayed
    • Black and white or colour copy is accepted
    • Issue date to be recorded as the date of submission
    • Expiry date to be calculated as 6 months from Issue date
    Expand
    titleContractor Engagement


    CertificationCertification RequirementsUpload RequirementsExamples

    Anchor
    contractorengagementform1
    contractorengagementform1
    WHC-FRM-Contractor Engagement – [SITE]

    This business rule was last updated by12/03/2021




    • Contracting Company: must be listed and match registered company in the system
    • Contractor Representative Name: must be listed (not applicable for Class A)
    • WHC Contractor Owner Name: must be listed
    • Site(s): must be ticked. Click HERE for a list of sites;
    • Scope of work: must be completed
    • Classification Result: must be indicated and responses to questions circled
    • Sub-contractors: must be completed
    • WHC HSE Document Review Acknowledgement: if classification is B or C the appropriate box must be indicated (not required for Class A)
    • Contractor Representative (System Acknowledgement): must be completed
    • WHC Contractor Owner (System Approval): must be completedApprovals to Engage Company for OLD FORM (Version 5.0) - Form needs to be signed but does not need to be from approved authorisers list. 
    • Approvals to Engage Company for NEW FORM (Version 67.0 OR 7 8.0): A Mine Operator or Delegate (Mine Site) or Relevant Manager (Off Site) associated with each site indicated on page 1 must sign off. These approvers must be on the Approved Authorisers list.
    • List of authorised approvers per site can be found HERE

    The latest version of this form is issue 78.0 – issue 5.0 will be accepted  providing that the Whitehaven Coal HSE Document Form 2 and Contractor Company Supervisor Nomination Form are uploaded with it (only the WHC-FRM-Contractor Engagement is required for Class A contractors).. The next previous version can also be accepted. 

    • Issue date to be recorded as Date of document approval by WHC Mine Operator or Delegate or Relevant Manager
    • Expiry date is 3 years from the date of approval

    Pegasus staff click here for additional business rule information prior to completing file verification

    Anchor
    subcontractorengagementform5
    subcontractorengagementform5
    WHC-FRM-Sub-contractor Engagement - [MAIN / FIRST / SECOND / THIRD / FOURTH / FIFTH /  SIXTH / SEVENTH] - [DIRECT / SUB] - [SITE NAME]

    This business rule was last updated by WHC on 01/03/2021



    IF submitted by a Primary Contracting Company:


    • Sub-contractor Company:
    • must
    •  must be listed and match a registered company in the system
    • Primary Contracting Company:
    • must
    •  must be listed and match
    • a
    • registered company in the system
    • Primary Contractor Representative:
    • must
    •  must be listed
    • WHC Contractor Owner Name:
    • must
    •  must be listed
    • Site(s): must be
    • ticked 
    • ticked -
    • Click 
    • Click HERE
    • for
    •  for a list of sites.
    • Scope of work:
    • must
    •  must be completed
    • Sub-contractor Management:
    • must
    •  must be completed
    • Primary Contractor Representative (Acknowledgement):
    • must
    •  must be completed
    Expand
    titleAppointment and Nomination Forms
    Anchor
    whcappointmentformswhcappointmentforms
    CertificationCertification RequirementsUpload RequirementsExamples
    • Name of Appointee: Contractor Owner as listed on WHC-FRM-Contractor Engagement
    • Name of Contracting Company: Must be listed and match company registered in onsite
    • This appointment applies at the following WHC Site(s) / Department(s): Site(s) must be ticked
    • WHC Contractor Owner:must complete name, signature and date.
    • Appointed By: Sign off must be completed by a Mine Operator or Delegate (Mine Site) or Relevant Manager (Off Site) associated with the relevant site/s ticked as per the Approved Authorisers list

    The latest version of this form is issue 2.0 – version 1.0 may also be accepted 

    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification

    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification

    Anchor
    contractorcompanysupervisornomcontractorcompanysupervisornom
    • Issue date to be recorded as Date of document signature by contracting company
    • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 - valid for 3 years

    Pegasus staff click here for additional business rule information prior to completing file verification

    Expand
    titleContractor Details
    CertificationCertification RequirementsUpload RequirementsExamples

    Head Contractor Details

    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in system

    P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

    Aust / Australia can be accepted in any of these forms if also listed as the name in the system

    Ttee (means trust) this is acceptable as long as the rest of the name matches

    • Head contractor Company details to be displayed
    • Black and white or colour copy is accepted
    • Issue date to be recorded as the date of submission
    • Expiry date to be calculated as 6 months from Issue date
    Anchor
    subcontractorformsubcontractorform
    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in system

    P/L / Pty LTD / Pty Limited can be accepted in any of these forms if also listed as the name in the system

    Aust / Australia can be accepted in any of these forms if also listed as the name in the system

    Ttee (means trust) this is acceptable as long as the rest of the name matches

    • Subcontractor Company details to be displayed
    • Black and white or colour copy is accepted
    • Issue date to be recorded as the date of submission
    • Expiry date to be calculated as 6 months from Issue date
    Expand
    titleContractor Engagement
    WHC-FRM-Contractor Engagement – [SITE]

    This business rule was last updated by12/03/2021

    WHC-FRM-Sub-contractor Engagement - [MAIN / FIRST / SECOND / THIRD / FOURTH / FIFTH /  SIXTH / SEVENTH] - [DIRECT / SUB] - [SITE NAME]

    This business rule was last updated by WHC on 01/03/2021

      Sub-contractor
    • WHC Contractor Owner (Sub-contractor Approval):
    • must be completed

    The latest version of this form is issue 5.0 – version 4.0 may also be accepted 

    CertificationCertification RequirementsUpload RequirementsExamples
    Anchor
    contractorengagementform1contractorengagementform1
    • Contracting Company: must be listed and match registered company in the system
    • Contractor Representative Name: must be listed (not applicable for Class A)
    • WHC Contractor Owner Name: must be listed
    • Site(s): must be ticked. Click HERE for a list of sites;
    • Scope of work: must be completed
    • Classification Result: must be indicated and responses to questions circled
    • Sub-contractors: must be completed
    • WHC HSE Document Review Acknowledgement: if classification is B or C the appropriate box must be indicated (not required for Class A)
    • Contractor Representative (System Acknowledgement): must be completed
    • WHC Contractor Owner (System Approval): must be completed
    • Approvals to Engage Company for OLD FORM (Version 5.0) - Form needs to be signed but does not need to be from approved authorisers list. 
    • Approvals to Engage Company for NEW FORM (Version 6.0 OR 7.0): A Mine Operator or Delegate (Mine Site) or Relevant Manager (Off Site) associated with each site indicated on page 1 must sign off. These approvers must be on the Approved Authorisers list.
    • List of authorised approvers per site can be found HERE

    The latest version of this form is issue 7.0 – issue 5.0 will be accepted  providing that the Whitehaven Coal HSE Document Form 2 and Contractor Company Supervisor Nomination Form are uploaded with it (only the WHC-FRM-Contractor Engagement is required for Class A contractors).

    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date is 3 years from the date of approval

    Pegasus staff click here for additional business rule information prior to completing file verification

    Anchor
    subcontractorengagementform5subcontractorengagementform5
    • Issue date to be recorded as Date of document approval by WHC
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification

    Expand
    titleHSE Documentation
    Anchor
    hsedocumentationhsedocumentationWHC-FRM-Contractor HSEManagement Plan Review – (SITE NAME) 

    Only required for Class C

    Form is valid for 3 years

    Contracting Company name much match the name of the company in Pegasus

    Form to be signed by WHC Contractor Owner, Department Manager and Mining Engineering Manager

    WHC-FRM-Contractor HSE Management Plan Review – Biodiversity Offsets

    Only required for Class C

    Form is valid for 3 years

    Contracting Company name much match the name of the company in Pegasus

    Form to be signed by WHC Contractor Owner, Department Manager and Mining Engineering Manager

    Issue date to be recorded as date of document approval by WHC Contractor Owner

    Image Removed

    •  must be completed

    The next previous version of the current form can be accepted.


    IF submitted by a Subcontracting Company:

    • Sub-contractor Company: must be listed and match registered company in the system
    • Primary Contracting Company: must be listed and match a registered company in the system
    • Primary Contractor Representative: must be listed
    • WHC Contractor Owner Name: must be listed
    • Site(s): must be ticked - Click HERE for a list of sites.
    • Scope of work: must be completed
    • Sub-contractor Management: must be completed
    • Primary Contractor Representative (Acknowledgement): must be completed
    • WHC Contractor Owner (Sub-contractor Approval): must be completed

    The latest version of this form is issue 56.0 – version 4.0 may also be accepted . The next previous version of the current form can be accepted.

    • Issue date to be recorded as Date of document approval by WHC Contractor Owner
    • Expiry date must align with the Primary Contracting Company’s WHC-FRM-Contractor Engagement – [SITE] form expiry

    Pegasus staff click here for additional business rule information prior to completing file verification



    Expand
    titleHSE Documentation

    Anchor
    hsedocumentation
    hsedocumentation

    WHC-FRM-Contractor HSEManagement Plan Review – (SITE NAME) 
    • Only required for Class C
    • Form is valid for 3 years
    • Contracting Company name much match the name of the company in
    Pegasus
    • the system
    • Form to be signed by WHC Contractor Owner, Department Manager and Mining Engineering Manager
    • Issue date to be recorded as date of document approval by WHC Contractor Owner
    • Expiry date to be recorded as 3 years from issue date


    WHC-FRM-Contractor HSE Management Plan Review – Biodiversity Offsets
    • Only required for Class C
    • Form is valid for 3 years
    • Contracting Company name much match the name of the company in
    Pegasus
    • the system
    • Form to be signed by WHC Contractor Owner, Department Manager and Mining Engineering Manager
    • Issue date to be recorded as date of document approval by WHC Contractor Owner
    • Expiry date to be recorded as 3 years from issue date