Document #Document DescriptionContractor Reference: Document RequirementsContractor Reference: Document ExamplesPegasus Administrator Reference: Document Requirements
SF00General and compliance plate photosGeneral photographs means digital photographs of the plant item normally taken from all sides, which clearly show the condition of the plant and demonstrate the existence of visible compliance requirements.  These photographs should be of a suitable size and image quality to permit enlargement on a computer screen without significant loss of image quality through pixellation, etc.

Compliance plate photographs shall mean digital photographs of all manufacturer's information plates, identification plates, and compliance information plates attached to the plant item or equipment.  Photographs of compliance plates must:
a. be taken in landscape mode and the plate must fill the width photo image, or be cropped to the width;
b. be taken such that all text on the information plate is clear and legible; and,
c. be taken at a suitable size and image quality (resolution) to permit enlargement on a computer screen without excessive loss of image quality or readability through pixellation, etc.

Pegasus staff CLICK HERE for additional information prior to file verification
SF01Design Risk AssessmentA formal risk assessment document that considers safety in the design phase of plant.  The design risk assessment could take many forms including a Safety in Design Report from the plant designer (or OEM), HAZOP study, Design FMEA, or one of the other design phase risk assessment methodologies that are described in ISO/IEC 31010. Refer to SafeWork Australia Safe Design of Plant Code of Practice and Safe Design of Structures Code of Practice.
Pegasus staff CLICK HERE for additional information prior to file verification
SF02Operation and Maintenance Risk AssessmentA formal documented risk assessment focussing on the hazards associated with the operation and maintenance of the plant or structure, and identifying controls to prevent or mitigate risks.
Pegasus staff CLICK HERE for additional information prior to file verification
SF03Fire Risk AssessmentA formal documented Fire Risk Assessment that complies with the requirements of AS 5062, including the assessment of fuel loads.
Pegasus staff CLICK HERE for additional information prior to file verification
SF04Hydraulic Risk Assessment (MDG41)A formal documented fluid power risk assessment focussing on fluid power hazards identified in MDG41.  If these hazards are assessed in an accompanying design risk assessment or operations and maintenance risk assessment document, then this requirement is waived. This should be noted on the applicable Site Access Approval Form, Approval to Enter Conditional Service Form, or Approval to Enter Service Form.
Pegasus staff CLICK HERE for additional information prior to file verification
SF05Registration Document A registration document e.g. certificate, issued by a registration authority e.g. NSW RMS, SafeWork, etc.  The registration document should clearly identify the registered plant usiing manufacturer, model and serial/VIN number, as a minimum.
Pegasus staff CLICK HERE for additional information prior to file verification
SF06eSafety Check Document (Pink Slip)Australian state government regulators no longer typically issue "pink slips" required for registration of vehicles.  Most of this is done online and the output of the NSW system is an eSafety Check Document, other states may differ.  NSW RMS also defers this requirement for vehicles less than 5 years old. The intent is for the Plant Owner to provide documented evidence that the vehicle has passed an inspection that complies with the state's regulations for vehicle road registration.
Pegasus staff CLICK HERE for additional information prior to file verification
SF07Brake Test Certificate / ReportFor road registered vehicles, this means a dynamic brake test certificate issued by a NSW RMS authorised inspector and in compliance with NSW RMS regulations for road registration. Where vehicles are registered in other states, then this means the equivalent certification provided in that state.
For non-road registered vehicles and plant, this means a dynamic brake test report completed by a competent and authorised person, which identifies the brake performance against specified acceptance criteria.  The report should include any printed output from the brake test equipment e.g. Milennium Brake-Testa.

Pegasus staff CLICK HERE for additional information prior to file verification
SF09NHVR Compliance CertificationA formal document from a regulatory authority or representative that certifies that a road going medium or heavy vehicle (GVM>4.5 tonnes) complies with the requirements of the National Heavy Vehicle Regulations (NHVR).
Pegasus staff CLICK HERE for additional information prior to file verification
SF10Brake Adjustment Report < 80% travelA brake adjustment report (or equivalent document) completed by a trained, competent and authorised mechanical tradesperson confirming the correct adjustment in accordance with OEM recommended practice and meeting specified acceptance criteria.
Pegasus staff CLICK HERE for additional information prior to file verification
SF11Service / Maintenance HistoryThe Plant Owner must provide a summary of the inspections, services and maintenance activities carried out on the equipment.  The minimum acceptable is the last completed routine services and maintenance work for past 12 months. If the plant is less than 12 months old, then the maintenance activities since delivery of the plant. 
Pegasus staff CLICK HERE for additional information prior to file verification
SF12Engineering Drawings (General Arrangements as a minimum)Engineering drawings must be provided for the plant item. As a minimum this includes one or more General Arrangement drawings showing plant elevations and plan views.  Other relevant engineering drawings can be provided including assembly drawings, sectional views, detail drawings, etc.  The intent is that engineering drawings are available that are required for the safe operation and maintenance of the plant.
Pegasus staff CLICK HERE for additional information prior to file verification
SF13Change Management HistoryA documented historical list of the modifications, alterations, and upgrades completed on the plant.  Where possible the reason for each change should be included. This includes upgrades and modifications issued by the OEM and any aftermarket modifications performed by the plant owner
Pegasus staff CLICK HERE for additional information prior to file verification
SF14Operation Manual / InstructionsMeans a digital / electronic copy of an OEM manual that describes how to operate the plant correctly, the operational hazards, the applicable safety precautions, and operating instructions.  This could be provided individually or as part of a larger Installation, Operation and Maintenance Manual. The manual must clearly show that it is applicable for the model of the plant.
Pegasus staff CLICK HERE for additional information prior to file verification
SF15Service / Maintenance ManualMaintenance or service manual supplied by the OEM for the specific make and model of plant
Pegasus staff CLICK HERE for additional information prior to file verification
SF16Commissioning ReportA commissioning checklist and report that records the individual checks, set up parameters, and critical tests that were conducted before placing the plant into service. The MAC Mechanical and Electrical Commissioning Checksheets should be incuded as applicable.
Pegasus staff CLICK HERE for additional information prior to file verification
SF17Thermographic Imaging ReportA thermographic survey report issued by a trained, competent and certified Level 1 thermography technician.  The report must include images and relevant temperature measurements.  Surface temperatures should not exceed 150 degrees C.
Pegasus staff CLICK HERE for additional information prior to file verification
SF18Confined space identification / registrationWhere the plant has a space that is deemed a confined space in accordance with the Australian Standards, a confined space register should be maintained by the Plant Owner and a copy submitted for the plant safety file.
Pegasus staff CLICK HERE for additional information prior to file verification
SF19Plant Design RegistrationSpecifically this is a copy of the certificate of design registration issued by SafeWork NSW, or an equivalent interstate regulatory authority.  An information plate fitted to the plant item should also clearly display the design registration number, so a photograph of this should also be provided.
Pegasus staff CLICK HERE for additional information prior to file verification
SF20Plant Item RegistrationSpecifically this is copy of the certificate of plant item registration that is issued by SafeWork NSW or equivalent insterstate regulatory authority.  The certificate must be current and in date at the time inspection.  A compliance information plate is also required to be fitted to the plant with the plant item regstration number engraved or stamped.  A photograph of this plate should be submitted as proof that the plate was in place at the time of inspection.
Pegasus staff CLICK HERE for additional information prior to file verification
SF21Pressure Vessel Test CertificateA certificate issued by certified pressure vessel inspector (AICIP PV Inspector) following completion of a statutory pressure vessel inspection in accordance with AS 3788.  The test certificate must be current at the time of inspection.
Pegasus staff CLICK HERE for additional information prior to file verification
SF22NDT ReportA non-destructive test report (NDT) is a report issued by a trained and competent NDT technician as part of an ongoing asset integrity management program.  Separate NDT reports are usually issued for each test method used, so there may be multiple reports submitted.  All NDT reports must be issued with a NATA accreditation.
Pegasus staff CLICK HERE for additional information prior to file verification
SF24Rim Register with OEM Test planThe plant owner of surface mobile plant or wheeled machinery with rims larger than 600mm (24 inch) must submit an extract from a rim register showing the identification of all rims fitted to the item of plant, and the inspection and test plan used to maintain integrity of the rims.  This could be a PDF file or a series of screen shots from a database, providing it meets the intent.
Pegasus staff CLICK HERE for additional information prior to file verification
SF25CraneSafe Certification (Green Sticker)A CraneSafe Green Sticker is affixed to a mobile crane after it has been inspected by a third party assessor.  The Green Sticker is affixed to the mobile crane.  A photograph of the CraneSafe Green Sticker affixed to the crane is adequate evidence provided it is current at the time of inspection.  An inspection report from the assessor should also be submitted if available.
Pegasus staff CLICK HERE for additional information prior to file verification
SF27Manufacturers inspection and test certificateAn inspection and test certificate issued in accordance with a prescribed standard, supplied by the OEM. Prescribe standard to be nominated on relevant form.
Pegasus staff CLICK HERE for additional information prior to file verification
SF28Overload Device Test CertificateA copy of a test record or calibration certificate for the overload device.  Test records must be current and performed by a competent person.
Pegasus staff CLICK HERE for additional information prior to file verification
SF29Vehicle / Trailer Mounted EWP- 6 Month Weight Test RecordPlease speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF31Earth Continuity TestingElectrical commissioning documents containing results of earth continuity tests
Pegasus staff CLICK HERE for additional information prior to file verification
SF32Voltage Reduction Device (VRD) Test RecordCopy of most recent Voltage Reduction Device (VRD) test record, signed by a competent person.
Pegasus staff CLICK HERE for additional information prior to file verification
SF33Commissioning of Electrical Work Form (MAC-ELC-FRM-014)Electrical commissioning documents including completed MAC-ELC-FRM-014 Commissioning of Electrical Work form.
Pegasus staff CLICK HERE for additional information prior to file verification
SF34Protection Relay testing <12 monthsElectrical commissioning documents incorporating Protection RelayTesting results and most recent annual test results completed by a competent person.
Pegasus staff CLICK HERE for additional information prior to file verification
SF35Lifting Points CertificationCopy of proof load test certificates for lifting points supplied by the manufacturer in accordance with AS 4991 Section 12 (or alternative equivalent standard). Alternatively, submission of engineering calculations by a professional engineer is also acceptable as per AS 4991.
Pegasus staff CLICK HERE for additional information prior to file verification
SF36Functional Safety assessment (critical Systems)Wade to provide
Pegasus staff CLICK HERE for additional information prior to file verification
SF40Isolation Procedure / InstructionsA work instruction or procedure describing the steps required to safely isolate the plant or machinery and remove hazardous energy.
Pegasus staff CLICK HERE for additional information prior to file verification
SF41Towing Procedure / InstructionsA documented work instruction describing the steps required to safely tow the plant or machinery if it becomes disabled.  This should include a description of the towing provisions installed by the OEM for towing.
Pegasus staff CLICK HERE for additional information prior to file verification
SF42Noise Test Report A noise test report issued by a competent person that demonstrates that the plant complies with MAC-ENC-PRO-075 Mobile Plant Noise Specification.
Pegasus staff CLICK HERE for additional information prior to file verification
SF43Fire system maintenance reportA maintenance history record showing the inspections, servicing and repairs carried out on any onboard fire protection/suppression system. At least previous 12 months required unless the plant is less than 12 months old.
Pegasus staff CLICK HERE for additional information prior to file verification
SF44Limited Exemption RequestA request from the contractor or plant owner for a limited exemption to operate only in the exempted and uncontrolled areas of the mine lease.
Pegasus staff CLICK HERE for additional information prior to file verification
SF45Lifting / Transport InstructionsA work instruction that describes the steps required to safely rig and lift the plant for transport.  The instructions should cover load restraint and special requirements for loading on transport.
Pegasus staff CLICK HERE for additional information prior to file verification
SF46Footing ValidationA document supplied by the installer showing validation or verification of the footings and anchor system prior to installation of the temporary building.
Pegasus staff CLICK HERE for additional information prior to file verification
SF50Certificate of Design ComplianceA certificate of design compliance issued by the equipment OEM, or a professional engineer, in accordance with a published Australian Standard. Prescribed standard to be nominated on relevant form.
Pegasus staff CLICK HERE for additional information prior to file verification
SF50-1GVM Upgrade – Second Stage Manufacture Certification or Design RegistrationA certificate of compliance issued by a licensed second stage manufacturer.  The second stage manufacturer must apply a compliance plate/label to the vehicle, so a photograph of the label is also recommended as evidence that it was attached at the time oof inspection.
Pegasus staff CLICK HERE for additional information prior to file verification
SF50-2Explosives Storage Box Manufacturer Identification PlatePhotograph of compliance plate fitted to the Explosives Storage Box is sufficient as evidence.  There may be more than one box as on a single plant item, so multiple photos may be sumitted evidence.
Pegasus staff CLICK HERE for additional information prior to file verification
SF51Functional descriptionA document provided by the OEM describing how the plant item is intended to operate and be used in practice.
Pegasus staff CLICK HERE for additional information prior to file verification
SF52Maintenance and inspection planA document describing the inspections and routine maintenance activities that will be implemented to maintain the plant integrity.  This may include time based replacement of components, frequency of inspections, inspection checklists, etc.
Pegasus staff CLICK HERE for additional information prior to file verification
SF53Weighbridge CertificateA certificate or printed output from a vehicle weighbridge showing the weight of the vehicle, plant item, or transportable plant.  Unless advised otherwise the certificate or print out must show the empty vehicle weight (kerb weight) as a minimum.  For trailers it is required to weigh the trailer loaded to determine the gross trailer mass (GTM) and the aggregate trailer mass (ATM).
Pegasus staff CLICK HERE for additional information prior to file verification
SF54Buoyancy AssessmentAn engineering calculation or design report issued by a professional engineer or OEM demonstrating the buoyancy of the floating plant, the amount of freeboard when loaded as designed, the loading conditions considered including wave height, wind speed, etc.
Pegasus staff CLICK HERE for additional information prior to file verification
SF55Structural Engineers CertificateA certificate of compliance, or letter, issued by a registered professional structural engineer stating the structural load conditions for the design of the structure, and compliance to relevant Australian Standards for design of structures.
Pegasus staff CLICK HERE for additional information prior to file verification
SF56Hydrostatic Leak Test ReportA test report issued by a competent engineer or certified inspector for hydrostatic leak tests conducted on the plant.  Typically, the report should show that the plant was able to hold a positive internal pressure (compressed air or nitrogen) for defined period of time without leakage.  This indicates that the plant is sealed and will not leak or taken on water.
Pegasus staff CLICK HERE for additional information prior to file verification
SF57Stability Assessment /ReportMeans a stability assessment or report issued by an competent and authorised engineer.  The stability requirements and the approach vary significantly for different types of plant, but the outputs of stability assessments describe the limits of operation for the plant.
Pegasus staff CLICK HERE for additional information prior to file verification
SF58Electrical Installation Certificate of Compliance to AS 3000Electrical commissioning documents
Pegasus staff CLICK HERE for additional information prior to file verification
SF59Gas Installation Certificate of Compliance to AS 5601A certificate of compliance for gas installtion work issued by a licensed gas fitter.
Pegasus staff CLICK HERE for additional information prior to file verification
SF60Plumbing Installation Certificate of Compliance to AS 3500A certificate of compliance for plumbing work issued by a licensed plumber.
Pegasus staff CLICK HERE for additional information prior to file verification
SF61Installation Drawings and InstructionsEngineering drawings provided by the OEM or plant designer showing the method of installation and the compliance requirements.
Pegasus staff CLICK HERE for additional information prior to file verification
SF62SchematicsEngneering drawings showing schematic representation of electrical, instrumentation and control, mechanical, hydraulic and pneumatic systems associated with the plant.  This includes Piping and Instrumentation diagrams (P&IDs), piping isometrics and process flow diagrams where applicable.  Red line mark ups are permitted for initial approval but must be updated with as built drawings when available.
Pegasus staff CLICK HERE for additional information prior to file verification
SF63Manufacturers Data Sheet / SpecificationAn OEM issued document incorporating all of the testing, ITPs, material certificates, welding quality records, and other manufacturer information pertaining to the construction and commissioning of the plant or structure.  Alternatively, a detailed OEM specification specific to the plant item may be acceptable.
Pegasus staff CLICK HERE for additional information prior to file verification
SF64Spare Parts ListA spare parts listing or spare parts manual for the plant item issued by the OEM.
Pegasus staff CLICK HERE for additional information prior to file verification
SF65Installation, operations and maintenance manualAn OEM manual for the installation, operation and maintenance of the plant item or structure.
Pegasus staff CLICK HERE for additional information prior to file verification
SF66Towing Points CertificationProof load testing certificate or OEM certification for the Towing Points installed on the machine by the OEM.  The working load limit shown on the documentation should match what is marked on the tow point.  An engineering calculation report issued by a registered professional engineer is also acceptable.
Pegasus staff CLICK HERE for additional information prior to file verification
SF67Insulation Resistance Test RecordsElectrical commissioning documents
Pegasus staff CLICK HERE for additional information prior to file verification
SF68Fall Arrest / Fall Restraint Anchor Point Test CertificatesTest certificates for Fall Arrest / Restraint Anchor Points issued by competent person in accordance with the relevant Australian Standard.  Test certificates must be current at the time of inspection.
Pegasus staff CLICK HERE for additional information prior to file verification
SF69TSH Statement Summary Card – Grey Card – (Scanned Copy)A scanned copy of the TSH Statement Summary Card (Grey Card) displayed on the Telescopic Handler.  This is usually in a clear pocket on the front of the weatherproof pouch used to hold the inspection logbook.  This must be readily available on the machine.
Pegasus staff CLICK HERE for additional information prior to file verification
SF70TSH/EWP Routine Maintenance Log Book (Scanned Copy)A scanned copy of the TSH/EWP Routine Maintenance Log Book stored on the machine.  This should be readily available in a weatherproof pouch or container.
Pegasus staff CLICK HERE for additional information prior to file verification
SF72Brake design standard from OEM

ISO 3450:2011 for wheeled and high speed rubber-tracked earth moving plant.

ISO 10265:2008 for all other crawler earth moving plant with maximum speed less than 20 km/h to include

The brake slope capability should be determined in accordance with ISO 3450-2011.


Pegasus staff CLICK HERE for additional information prior to file verification
SF73Ergonomic assessmentPlease speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF74Fire risk assessment in accordance with AS5062Please speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF75Fire system service history in accordance with AS1851Please speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF76List of SDS coming to site and approval in site ChemAlert systemPlease speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF77Rim certificate of conformance to AS4457 provided for rims over 600mm.Please speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF78Vibration levels – Whole bodyPlease speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF79Visibility assessmentPlease speak to your contractor owner for clarification
Pegasus staff CLICK HERE for additional information prior to file verification
SF80Pressure Safety / Pressure Relief Device Test and Calibration CertificateA certificate issued by certified pressure equipment inspector (AICIP Inspector) following completion of a statutory pressure equipment inspection, or calibration, in accordance with AS 3788.  The test/calibration certificate must be current at the time of inspection.
Pegasus staff CLICK HERE for additional information prior to file verification
SF81Proof load test certificateAn inspection and test certificate issued in accordance with a prescribed standard, supplied by the OEM.
Prescribed standard to be nominated on relevant form.

Pegasus staff CLICK HERE for additional information prior to file verification